New pool and spa, Mims

A new pool and raised spa on an open rural lot: excavation and formed shell, a stacked stone spa surround, wide poured deck and a full equipment pad with automation.

Completed pool and raised spa in stacked stone, Mims
Scope
New build
Location
Mims
Interior
CL Industries Quartz, Super Blue
Completed
2023

Before and after

Drag to compare.

Back yard before excavation on a rural lot, MimsBeforeAfter
The job

What we found

No pool in the backyard.

How we sequenced it

Layout, excavation, steel and forms, shotcrete, then waterproofing on the shell. Plumbing, tile and the deck followed, then bond coat, the equipment, a CL Industries Quartz interior in Super Blue, and an Orenda startup.

The shape was built for volleyball, deep through the middle, with a tanning ledge and a spa.

Where it landed

You can still play volleyball across the pool, which is what it was shaped for. There is a tanning ledge and a spa alongside it. The homeowner is extremely happy, and it is a good place to relax.

Spoil piled as the pool excavation begins, Mims
Pool excavation opened up behind the house, Mims
Excavation with gravel base laid, Mims
Sonotube form set for the raised spa, Mims
Form boards and pipe laid out around the excavation, Mims
Formed pool shell with bracing in place, Mims
Steel and formwork through the pool shell, Mims
Formed and reinforced shell ready for shotcrete, Mims
Poured deck around the finished shell, Mims
Raised spa formed within the new deck, Mims
Shell and spa with the deck poured around them, Mims
Pool shell and deck seen across the rural lot, Mims
Raised spa and deck before the interior finish, Mims
Shell interior with plumbing stubs before finishing, Mims
Spa interior prepared for finish, Mims
Spa bench and step detail before finishing, Mims
Shell prepared with returns set before the finish, Mims
Return fittings set in the shell wall, Mims
Plumbing stubs left proud of the shell before finishing, Mims
Light cable run into the shell before the finish, Mims
New pool filled and clear beside the raised spa, Mims
Valve manifold and filter at the equipment pad, Mims
Pool electrical panel wired at the house wall, Mims
Completed pool and spa seen from the deck corner, Mims
Finished pool and raised spa with open pasture beyond, Mims
Completed pool, spa and deck, Mims
Raised spa and coping detail in the finished pool, Mims

What went in

InteriorCL Industries Quartz, Super Blue · new pool construction

Questions we get on this kind of job

How long does a pool renovation take?

It depends on scope, permitting, weather, and material lead times. A builder who quotes a day count before seeing your shell is guessing. What you should expect is a dated schedule before work starts, and that is what we give you.

Why does coping go on before waterline tile?

Setting coping first means the tile band is only cut once, and it lets the waterproofing run continuously behind both. Tiling first forces a second cut and leaves a break in the waterproofing at the joint most exposed to sun and pool chemistry.

When do I pay?

Milestone billing. Each stage of the schedule triggers its own invoice, and a stage is only billed once it's complete. Nothing is billed ahead of the work.