A shotcrete shell is not finished when the rig drives away. It is at the start of a process that decides how strong it will ever be.
What the shell is doing
A shell does not get hard simply by drying out. It gets hard through a chemical reaction between the cement and the water in the mix, and that reaction keeps building strength for weeks as the shell cures toward the strength it was designed for.
That reaction needs the water to keep going, so curing is about controlling how fast the shell loses it. The shell is watered every day so it dries slowly and evenly instead of all at once. Let it dry out or heat up too fast and two things happen. The surface shrinks faster than the concrete beneath it, which is where shrinkage and stress cracks come from. And wherever the concrete dried early, the reaction stopped early, which leaves that concrete weaker and more brittle.
What waits, and what happens when a builder does not
Tile, coping and plaster all wait until the shell has cured.
A finish applied to a shell that is still curing can lead to problems down the road. The common one is delamination: the finish lets go because the shell was still changing underneath it. Tile pops off for the same reason. And a shell that never got a proper cure is brittle, low-strength concrete with stress fractures in it. None of that shows on the day.
A builder who starts coping early is trading your shell's strength for time on the calendar. It is not a trade you get to reverse.
What keeps moving
The time is not wasted. Partway through the cure the form boards come off, and backfill, compaction, trenching and the rest of the plumbing all happen inside the cure window. The main drain lines are already under pressure when the backfill goes in, and the rest are tested as soon as they are finished, so if a line gets hit, we know right away.
What to ask
When is the shell shot, when does the coping start, and what happens in between. The answer to the last one should be a list of work, not a gap.