The plaster is troweled by hand, the pool is washed and filled, and from the deck it looks finished. It is not. A new interior keeps curing under the water, and whatever goes into that water in the first week is working on a surface that has not finished setting.
That is why we run startup ourselves, on the Orenda startup method, rather than handing the pool to whoever services it. It is our finish, so the first week is our job.
What you do that week
Less than you would think, because we're handling the startup.
- Use the pool like normal. Swim in it. It is your pool.
- Leave the equipment running around the clock. The water needs to keep moving while the finish cures.
- Do not add any chemicals we have not prescribed. However well meant, a product from the store is the quickest way to mark a new finish.
- Brushing is taken care of. Extra brushing is good for a new interior, and we do it for you.
What we are doing in the water
We use the Orenda method to balance the water's LSI, the Langelier Saturation Index. It is the measure of whether water will leave scale on a surface or pull calcium out of it. In practice that means:
- pH between 7.4 and 7.6.
- Alkalinity kept in check. The right number depends on the rest of the water, but it is typically between 70 and 120 ppm.
- Stabilizer at the bare minimum that holds chlorine in the water, typically 30 ppm.
- Liquid chlorine. We avoid tabs, feeders and salt systems while the plaster is curing.
Calcium hardness has to reach 300 within the first week. Get there too fast and the pH swings, which scales the finish. Never get there at all and the water balances itself by pulling calcium out of the cement, which stains the surface and eventually damages it. Dosing is paced deliberately, a few pounds at a time.
That is the whole reason the first week cannot be guessed at. It is arithmetic, done on a schedule, against a written procedure.
What a startup gone wrong looks like
When we are called out to somebody else's new pool, it is almost always one of two things: too many chemicals, or not enough.
Too many. A lot of companies do not want to do the math or read through the procedure. Overdose a new pool and you can destroy the finish. It is easy to use too much acid and etch the color right out of it. The wrong product does its own damage too: granular trichlor sinks, sits on the floor of the pool, and bleaches the plaster where it lands.
Not enough. The other failure is doing nothing. Left alone, the water balances itself one way or another, and typically that means scaling.
Either way the pool is new, the finish is already marked, and there is no undoing it.
What to ask
Who runs the first week, what procedure do they follow, and who is brushing. If the answer is that it becomes your job the day the pool is full, that is the week your finish is most at risk.