Everything checked at this stage gets buried in the shell for good. It is the last point where any of it can be fixed at a reasonable cost.

By the time the shotcrete rig arrives, the hole is dug, the steel is tied, the drain lines are in and the forms are set. A few long hours later all of it is inside or underneath a concrete shell. So before anything is shot, it gets checked: by us, and by the permitting department.

What we check

  • Layout and elevation. The pool sits where the drawings put it, at the height they put it.
  • Rebar spacing. The steel is where the engineered plans call for it.
  • Bonding. More on this below, because it is the one that gets missed.
  • Dewatering. On this coast the hole has to be held in a condition the shell can be shot in. Water left standing in the hole ends up in the shotcrete, and extra water makes it weaker right out of the gate.

The permitting department typically comes out and inspects the bonding and the plumbing pressure as well.

Bonding, and why more points is safer

Bonding connects the steel and the metal in and around the pool with a wire run back to the equipment, so everything a swimmer can touch sits at the same voltage.

We bond to each side of the pool, so four points at a minimum, and more on a larger pool. More points means redundancy: if one is broken, damaged or missing later in the project, the others are still doing the job.

Water bonding is the one most people forget. Pools used to have large metal light niches set into the wall. Everyone has switched to nicheless lights, so that metal in the water is gone, and a lot of builders forget the water still needs bonding. We install water bonding points through the skimmer or the umbrella holders.

Every line stays under pressure

When a line gets pressure tested depends on the line.

  • Main drains are tested right out of the gate. The rebar is bent around them, and their pipe leaves out the back of the shell low to the floor. Once the form boards come off and the ground is compacted, they are the hardest lines on the pool to reach. So before the shell is shot, they are plumbed, pressure tested at 60 psi and brought out away from the pool.
  • The rest of the plumbing is tested when it is finished. Those lines are easier to reach and easier to replace, so they are tested once the plumbing stage completes them.

From then on, every line stays charged for the length of the project, through backfill, decking and everything else, until the equipment is set. That is so nobody hits a line without knowing it. If a machine or a stake finds a pipe, the pressure drops and we know that day, not after the line is buried or the pool is finished and filled.

What to ask

Who inspects before the shell is shot. How many bonding points there are, and whether the water is bonded. And whether the plumbing is still under pressure while the rest of the build goes on around it.

Luke GellFlorida Certified Pool/Spa Contractor CPC1460652 · Cocoa, FL

Want yours walked?

Luke does the walk-throughs himself and will tell you straight whether your pool needs fixing or redoing.

Call 321-890-4676Book a walk-through