A pool renovation looks simple from the outside. The old surface comes off, a new one goes on. In practice there are seven distinct stages, several of them dependent on each other in ways that aren't obvious, and the cost of getting the order wrong doesn't show up until the pool has been full of water for a year or two.
This is how we run it, and why.
1. Drain and chip-out
The pool drains first thing in the morning, which takes an hour or so, and demolition starts the same day. There's no reason for the shell to sit empty overnight waiting on a crew.
While the water is going down, someone stands there and watches it. That sounds obvious and it frequently doesn't happen. The relief valve gets confirmed open, the shell gets watched as it draws down, and the discharge point gets walked while water is flowing, because water finds places nobody expected.
What holds an empty shell down is the relief valve, not the pump. The hydrostatic relief valve in the floor of the pool equalizes groundwater pressure under it. Pumps exist so the crew can work in a dry shell. What matters is that the relief is actually open, and on a lot of pools it isn't: a shell shot in wet conditions often has the relief covered up, and if the plug doesn't get pulled on one of those, an empty pool becomes a boat and floats with the water table. So the valve gets confirmed before the water goes down, and there's a core drill on the truck to cut a new one if it has been buried.
Then the old interior comes out. All of it.
This is the first real decision point, and it's where a lot of renovations are quietly compromised. The tempting shortcut is to chip out the areas that have visibly failed and leave the plaster that still looks sound. It saves a day of labour and a dump run. It also means the new finish is bonded to material that has already started letting go, and that material takes the new interior with it when it goes.
2. Waterproofing
This follows cleanup with no gap day. Rough spots at the coping and tile lines get ground flat first. That's not for looks. A membrane stretched across a gap isn't waterproofing anything.
The tile band gets two coats of a cementitious waterproofer that stays more flexible than most, because that band moves more than any other part of the pool. Every pipe penetration gets a different waterproofer, a more rigid one. There's no cure wait afterward; the next stage can begin immediately.
Worth being precise here, because it's the single most confused pair of products in pool renovation: the tile band waterproofer and the bond coat are two different products doing two different jobs. The first goes on now, before coping and tile, and flexes with the joint. It keeps water, and the white efflorescence it carries, out of the tile line. The bond coat goes on much later, over the entire shell, immediately before plaster. It holds the new interior to the pool and lets the plaster hydrate at a controlled rate, which is what makes a strong interior with an even color. Between them, and the waterproofer on every penetration, the whole shell gets a watertight finish, not just the tile line. Doing one and calling the other handled is a common mistake.
3. Coping and deck
Waterproofing, then thinset, then a mortar float to bring everything to height, then thinset again to set the coping. The mortar is doing the levelling; the thinset is what bonds it to the surface underneath.
Coping goes on a full bed. We hold a minimum of 95% coverage under every piece. That's higher than the industry generally manages, and low coverage is why coping lifts.
Coping and deck go in before tile, with one exception. Setting tile first and then building coping up to that level is faster, and it's how a great many pools get done. It leaves a cold joint directly behind the tile, at the most sun-exposed and chemically-exposed point on the entire pool. When waterline tile pops off years later, that joint is usually why.
That exception is poured concrete coping. It is part of the deck itself rather than a separate element, so it cannot go in ahead of the tile. The tile is set first and held to the top of the bond beam, never above it, and the coping is poured over it. It still gets waterproofed, but instead of a decoupling membrane it needs an expansion or slip joint, so the deck can move independently of the tile.
4. Waterline tile
Now there's a straight, finished edge to set to. The tile band gets cut once instead of twice, and the waterproofing behind it is continuous rather than interrupted.
No cure window is needed between coping and tile.
5. Bond coat
Fittings can't go in until tile is set, so this stage waits. Existing fittings get chipped around so flush-mount water stops can be installed, with fittings color-matched to the new interior, and penetrations get floated and sealed. The drains, the fittings and the light niches are pressure tested. Then everything gets taped off.
Then the whole shell is pressure-washed with a turbo nozzle. This isn't cleaning for its own sake. It's what gives the bond coat something to grip. A shell that wasn't washed properly, or was washed weeks earlier and has been sitting dirty since, is a new interior that will fail early no matter what goes on top of it.
The bond coat is rolled over the entire shell with an aggressive texture, so the plaster has as much as possible to hold on to, and it lets the plaster hydrate at a controlled rate once it's on.
Ten working days from bond coat to plaster. Thirty calendar days is the outside limit. The longer a coated shell sits, the more likely it needs washing again — particularly if dewatering was switched off and the shell got dirty. This is why we keep pumps running through that window even when the hole doesn't strictly need to be dry.
6. Plaster and fill
The interior is shot in one continuous application. A pebble finish that gets interrupted shows the seam permanently, so the crew starts at first light and doesn't stop until it's in. For the same reason, plaster never splits across a weekend.
The day before, someone walks the pool specifically to make sure nothing can stop it: tape off the fittings, confirm the color against what the client selected, stage the startup chemicals, verify the equipment runs. A plaster crew standing around because a drain cover is missing is an expensive morning.
Wash and fill happen in the same visit. There's no separate fill stage.
7. Startup chemistry
This is the stage most builders hand off, and it's the one that decides what the finish looks like for the next fifteen years.
A new pebble interior is still curing when the water goes in. The water chemistry in that first week isn't maintenance. It's the last construction step, working on a surface that hasn't finished setting.
Calcium hardness has to reach 300 within the first week. Get there too fast and the pH swings, which scales the finish. Never get there at all and the water balances itself by pulling calcium out of the cement, which stains the surface and eventually damages it. Dosing is paced deliberately, a few pounds at a time.
We do this ourselves, on the Orenda startup method, rather than handing it to whoever services the pool. It's our finish. If it discolors in the first month, that's our problem, and the only way to be sure it doesn't is to run it.
Why any of this matters to you
You're not going to supervise a renovation, and you shouldn't have to. But nearly every one of these decisions is invisible by the time the pool is full, and most of them save a contractor real money in the short term at your expense in the long term.
You don't need to remember the sequence. Remember the three questions: will you chip out all of it, does coping go on before tile, and who handles the first week. Any builder worth hiring will answer without hesitating.